Tilapia Hatchery and grow out project Madagascar Thanks to Loha for this
About the project: it's a project build by an NGO who is MIDEM(Mission Independante pour le Developpemnet et l'Education a Madagascar) funded by NORAD/NORGES VEL of Norway
With the target: to increase the income of farmers to 60 USD/month by fish farming(Tilapia). But using the local strain we didn't reach the target; slow growth, long cycle and low profitability) then we decide to import the GIFT and BIG NIN of Nam Sai Farm Thailand Co.Ltd on July 2013 and import feed from LFL Feed company Mauritius until now when the project become TILAPIA DE L'EST on Jan 2015.
Now we have 69 ponds working and 85 ponds under construction.
Our technical key indicators are:
Density on stocking: 3/ cubic m(All male Tilapia at 98%),semi intensive culture
Average pond dimension: 700 sq m or more
Average Mortality: 12%
Average FCR: 1.2
Period: 140 Days from at least 0.4g ABW of fingerlings on stocking
ABW per pond on harvest: 240g with an average of production at 350kg per pond
We are using the Asian method to get all male fingerlings using 17 alpha methyl testosterone>
We made protocols with our consultant from Norway Sir Morten Frost from pond building to harvest and commercialisation.
I'm now in charge on Broodstock management, eggs incubation, Sex reversal process, nursery and Packing and fingerlings delivery to farmers (transportation), so all about hatchery since 2011 and an integrated hatchery is now being built now.
But now our problem now is importation, we depend a lot on LFL Mauritius and USD exchange rates now increasing vis a vis of our money value then the cost of feed is very high for the farmers.
Then I've got the idea to create the first company in Madagascar who will provide the best feed quality for aquaculture at the lower possible price (the legendary floating pellet from Asia).
Our farmers will increase to reach 250 in number next year and the demand for feed will be higher. The target of TILAPIA DE L'EST by 2019 is 300 ponds and 600 by 2023 but 300 will be reached soon at least in the end of 2016 as we projected, because everyone wants to farm Tilapia with us now since it become profitable for them.
So if you know someone or an organisation who can fund this project to build a company for aquaculture feed let me know, it's a very big business opportunity down here now since the demand is very high.
I'm just talking about the Tilapia del'Est but a lot of other customers and other organisation like APDRA want this type of feed also. We are proud to be the first project who is successful in tilapia farming in Madagascar until now.
It's quite a long process ahead but it's all about us and aquaculture is developing down here.
Best Wishes,
Loha
Tilapia écloserie et grossissement des projets Madagascar Merci à Loha pour cette
À propos du projet: il est une construction du projet par une ONG qui est MIDEM (Mission Indépendante for the Developpement et l'éducation d'un Madagascar) financé par NORAD / NORGES VEL de la Norvège
Avec l'objectif: augmenter le revenu des agriculteurs de 60 USD / mois par la pisciculture (Tilapia). Mais l'utilisation de la souche locale nous n'a pas atteint la cible; croissance lente, cycle long et à faible rentabilité), alors nous décident d'importer le don et le BIG NIN de Nam Sai Farm Thaïlande Co. Ltd en Juillet 2013 et l'alimentation de l'importation de LFL Flux entreprise Maurice jusqu'à présent lorsque le projet devienne TILAPIA DE L'EST sur janvier 2015.
Maintenant, nous avons 69 étangs de travail et 85 étangs en construction.
Nos indicateurs clés techniques sont:
Densité de peuplement: 3 / m cube (tous de sexe masculin Tilapia à 98%), la culture semi-intensif
Étang moyenne dimension: 700 mètres carrés ou plus
La mortalité moyenne: 12%
Moyenne FCR: 1.2
Période: 140 jours d'au moins 0,4 g ABW d'alevins sur le stockage
ABW par étang sur la récolte: 240g avec une moyenne de production de 350 kg par étang
Nous utilisons la méthode asiatique pour obtenir tous les alevins mâles utilisant 17 alpha de testostérone de méthyle>
Nous avons des protocoles avec notre consultant de la Norvège Monsieur Morten Frost, de la construction de l'étang de récolter et de commercialisation.
Je suis maintenant en charge la gestion du stock de géniteurs sur, les oeufs d'incubation, le processus d'inversion de sexe, de pépinière et d'emballage et de la livraison des alevins aux agriculteurs (transport), de sorte que tous propos écloserie depuis 2011 et une écloserie intégrée est en cours de construction aujourd'hui.
Mais maintenant, notre problème est maintenant l'importation, nous dépendons beaucoup LFL Maurice et USD taux de change de plus en plus maintenant vis à vis de la valeur de notre argent, alors le coût des aliments est très élevé pour les agriculteurs.
Ensuite, je dois l'idée de créer la première entreprise à Madagascar qui fournira la meilleure qualité d'aliments pour l'aquaculture au prix inférieur possible (la légendaire de granulés flottants d'Asie).
Nos agriculteurs vont augmenter pour atteindre 250 en nombre l'année prochaine et la demande pour l'alimentation seront plus élevés. La cible du tilapia DE L'EST en 2019 est de 300 étangs et 600 d'ici 2023, mais 300 sera atteint dès au moins à la fin de 2016, comme nous avions prévu, parce que tout le monde veut cultiver Tilapia avec nous maintenant, car il devient rentable pour eux.
Donc, si vous connaissez quelqu'un ou une organisation qui peut financer ce projet de construction d'une société pour l'alimentation aquacole laissez-moi savoir, il est une très grande opportunité d'affaires ici aujourd'hui car la demande est très élevée.
Je parle simplement de l'Tilapia de l'Est, mais beaucoup d'autres clients et d'autres organisation comme APDRA veulent ce type d'alimentation aussi. Nous sommes fiers d'être le premier projet qui a réussi dans l'élevage du tilapia à Madagascar jusqu'à maintenant.
Il est un processus assez long avant mais il est tout autour de nous et de l'aquaculture se développe ici.
Amicalement
Loha
Institute of Aquaculture, University of Stirling UK
www.aqua.stir.ac.uk<http://www.aqua.stir.ac.uk/>
Follow Daily updated Facebook sites (news, publications, videos, employment, funding, investment and other) for:
Inst of Aquaculture Stirling Scotland UK<https://www.facebook.com/pages/Institute-of-Aquaculture-Stirling-Scotland-U…>
SARNISSA African Aquaculture Network <https://www.facebook.com/sarnissaafrica?ref=hl>
Aquaculture Enterprise Malawi<https://www.facebook.com/pages/Aquaculture-Enterprise-Malawi/57280560286237…>
SEAT Sustaining Ethical Aquaculture Trade Asia (SEAT) <https://www.facebook.com/SEATGlobal?ref=hl>
[IoA_logo square 2]<http://www.aqua.stir.ac.uk/> [IOA]
Bonjour à tous,
Actuellement en fin de formation en tant que chef de projet en aquaculture,
j'aimerai travailler dans une ferme aquacole en Afrique, que se soit en
écloserie ou sur des sites de grossissement.
J'ai eu une première expérience en Côte d'Ivoire où j'ai participé au
projet d'installation d'une ferme sur une lagune.
J'ai étudié les milieux d'élevage propre à la Côte d'Ivoire et dimensionné
les infrastructures nécessaires, afin d'établir les plans de productions
adéquates pour le bon fonctionnement de la ferme.
Je recherche des contacts afin de parfaire ma formation et apporter mes
compétences pour améliorer le volume des productions aquacoles en Afrique.
Je suis bilingue (français, anglais) et disponible de suite pour étudier
toutes propositions de travail.
Merci à tous de l'attention que vous porterez à ma démarche.
M. Coyère Jean-Luc
From: PAEPARD(a)dgroups.org [mailto:PAEPARD@dgroups.org] On Behalf Of ghare.tropicultura(a)belgacom.net
Sent: 18 December 2015 10:15
To: Platform for African - European Partnership in Agricultural Research for Development Phase II (PAEPARD II)
Subject: [paepard] TROPICULTURA 2015 (33/4)
Dear readers of Tropicultura, the 4th issue of the volume 33 published in 2015 is available on our internet site. You can download it on following link
http://www.tropicultura.org/eng/content/v33n4.html
Chers lecteurs de Tropicultura, le numéro 4 du volume 33 de 2015 est disponible sur notre site internet. Vous pouvez le télécharger sur le lien suivant :
http://www.tropicultura.org/content/v33n4.html
Queridos lectores de Tropicultura, el número 4 del volumen 33 de 2015 está disponible sobre nuestro sitio internet. Usted puede cargarlo mediante el lazo siguiente
http://www.tropicultura.org/spa/content/v33n4.html
Geachte lezers van Tropicultura, het nummer 4 van volume 33 gepubliceerd in 2015 is beschikbaar op onze website. U kunt het downloaden op de volgende link:
http://www.tropicultura.org/dut/content/v33n4.html
G. HARELIMANA
Editorial Office TROPICULTURA
Phone 0032 (2) 540 88 60
Website : http://www.tropicultura.org/
FacebookTROPICULTURA<https://www.facebook.com/pages/Agri-Overseas/393478047506146?sk=timeline>
TwitterTROPICULTURA<https://twitter.com/TropiculturaBE>
You are receiving this message because you are a member of the community Platform for African - European Partnership in Agricultural Research for Development Phase II (PAEPARD II)<https://dgroups.org/paepard>.
View this contribution on the web site<https://dgroups.org/_/j187gj1s>
A reply to this message will be sent to all members of Platform for African - European Partnership in Agricultural Research for Development Phase II (PAEPARD II).
Reply to sender<mailto:ghare.tropicultura@belgacom.net> | Unsubscribe<mailto:leave.PAEPARD@dgroups.org>
Chers collègues,
Nous avons le plaisir de partager avec vous l’article préparé et disséminé par GWI concernant l’approbation par les ministres de l’eau de la CEDEAO du projet de directive sur le développement d’infrastructures hydrauliques en Afrique de l’Ouest.
Cordialement,
----------------
Les ministres de l'eau de la CEDEAO conviennent de construire des barrages plus équitables
Les ministres en charge des ressources en eau des 15 états membres de la Communauté Économique des États de l’Afrique de l’Ouest (CEDEAO) ont approuvé un projet de directive sur le développement d’infrastructures hydrauliques en Afrique de l’Ouest qui veillera à ce que les aménagements futurs, notamment les grands barrages, respectent l'environnement et profitent à tous, y compris aux populations affectées.
« L'objectif déclaré du dit projet de directive est de faire en sorte que les considérations d'ordre écologique, économique et social soient davantage prises en compte dans le développement de projets transfrontaliers d'infrastructures hydrauliques en Afrique de l'Ouest afin de garantir leur viabilité » explique Mahamane Dédéou Touré, du Centre de Coordination des Ressources en Eau de la CEDEAO.
À travers cette approbation, les gouvernements de la région réitèrent leur engagement envers une approche commune et concertée en matière de gestion durable des ressources en eau dont leurs populations ont besoin pour vivre.
Dans le contexte des changements climatiques, l'énergie et la production alimentaire sont des grandes priorités à l'ordre du jour international de la COP21 à Paris. Ce sont aussi généralement les moteurs derrière l'intérêt national et régional accordé aux projets d'irrigation et de barrage complexes et onéreux —150 barrages sont déjà construits en Afrique de l'Ouest et 40 sont actuellement en construction ou en projet. Mais les expériences passées dans la région révèlent que les bénéfices générés par les barrages atteignent rarement les populations locales dont les droits et les moyens d'existence sont les plus directement affectés.
À Kandadji au Niger et à Samendéni au Burkina Faso, respectivement 38000 et 40000 personnes sont déplacées par des barrages en construction. En Guinée, le barrage de Fomi déplacera 48000 personnes. Les communautés qui accueillent ces personnes déplacées sont également fortement touchées.
Jamie Skinner, directeur de la Global Water Initiative en Afrique de l'Ouest, déclare « si elle est mise en œuvre, la directive marquera un profond changement dans la façon dont les barrages sont conçus et construits en Afrique de l'Ouest, en veillant à ce que les populations aux niveaux local et national aient accès aux bénéfices de manière équitable. »
Parmi les éléments clés de la directive, on peut citer le besoin de garantir la participation des populations affectées aux prises de décision en toute connaissance de cause ainsi que le recours à des cadres juridiques et procéduraux plus robustes pour accorder aux populations locales des bénéfices tels que les terres agricoles, l'électricité, l'eau potable, les pâturages et les zones de pêche.
Suite à cette approbation des ministres sectoriels, le Conseil des Ministres Statutaires de la CEDEAO devra officiellement adopter la directive lors d’une prochaine session pour qu’elle s’impose à ses États membres. Ceux-ci devront ensuite amender ou adapter leurs mesures législatives et réglementaires au besoin, dans un délai de trois ans à compter de son entrée en vigueur. La CEDEAO sera chargée de l'évaluation de la mise en œuvre de la directive tous les cinq ans.
Si les gouvernements et les investisseurs ne respectent pas la directive, ils risquent dans la pratique d'appauvrir davantage les populations locales affectées ou, pire encore, de déclencher des conflits liés aux ressources naturelles et au foncier. Le risque de conflit ne se limite pas aux frontières nationales — la plupart des grands aménagements sur les fleuves d'Afrique de l'Ouest concernent plus d'un pays. Le rôle des organismes de bassin transfrontalier – tels que l'Autorité du Bassin du Niger – est donc reconnu comme extrêmement important.
Le projet de directive a été officiellement approuvé lors de la 4e session du Comité ministériel de suivi de la CEDEAO pour la gestion intégrée des ressources en eau (GIRE) en Afrique de l'Ouest, qui s'est tenue à Dakar, au Sénégal, le vendredi 27 novembre 2015, sous la présidence du ministre de l'Hydraulique et de l’Assainissement du Sénégal. Elle est fondée sur les « Lignes directrices pour le développement d’infrastructures hydrauliques en Afrique de l'Ouest » élaborées au terme d'un dialogue régional de deux ans entre les États membres, les organismes de bassin et la société civile démarré en 2009, sous la direction du Centre de Coordination des Ressources en Eau de la CEDEAO, avec le soutien de l'Union internationale pour la conservation de la nature (UICN) et l'Institut international pour l'environnement et le développement (IIED).
/FIN
Ressources associées :
• Reportage Africable sur le Comité ministèriel de GIRE de la CEDEAO et le projet de directive [https://www.youtube.com/watch?v=rLc-M7nDuYA]
• Niger : un fonds local pour partager les bénéfices du barrage de Kandadji [Fiche d'information de la GWI] http://gwiwestafrica.org/fr/niger-un-fonds-local-pour-partager-les-bénéfice…<http://gwiwestafrica.org/en/niger-local-fund-share-benefits-kandadji-dam>
• Barrages en Guinée : des propositions pour réussir le développement local [Fiche d'information de la GWI] http://gwiwestafrica.org/fr/barrages-en-guinee-des-propositions-pour-reussi…<http://gwiwestafrica.org/en/dams-guinea-proposals-achieving-local-developme…>
• Lignes directrices pour le développement d'infrastructures hydrauliques en Afrique de l'Ouest http://cmsdata.iucn.org/downloads/ccre_cedeao_lignes_directrices_barrages_1…
• Barrage de Samendéni : Le cri du cœur des populations affectées [Article de presse] http://lefaso.net/spip.php?article67654
Contact :
Pour plus d'informations, des photos ou des entretiens, nous vous invitons à contacter : Lucile Robinson, Chargée de programme – Gestion des connaissances et des communications (Global Water Initiative – Afrique de l'Ouest), e-mail : lucile.robinson(a)iied.org<mailto:lucile.robinson@iied.org>.
Notes aux rédacteurs :
La 4e session du Comité ministériel de suivi de la Gestion intégrée des ressources en eau (GIRE) en Afrique de l'Ouest a été précédée, les 24 et 25 novembre, par la 10e session du Comité technique des experts. Les réunions ont été accueillies par le ministère de l'Hydraulique et de l’Assainissement du Sénégal et organisées par le Centre de Coordination des Ressources en Eau de la CEDEAO, l'UICN et IIED. Elles ont été financées par la Commission de la CEDEAO, UK Aid (DFID) et la Fondation Howard G. Buffett à travers la Global Water Initiative (GWI) en Afrique de l'Ouest, et l'Agence suédoise de développement international (SIDA) à travers le programme Partenariat pour la gouvernance environnementale (PAGE) de l'UICN.
Pour obtenir un complément d'information sur la Global Water Initiative (GWI) en Afrique de l'Ouest : www.gwiwestafrica.org<http://www.gwiwestafrica.org>
Jérôme KOUNDOUNO
Coordinateur Régional
Global Water Initiative (GWI) - Afrique de l'Ouest
Union Internationale pour la Conservation de la Nature
Dakar, Sénégal
Tél : (+221) 77 102 53 57
www.gwiwestafrica.org<http://www.gwiwestafrica.org/>
www.iucn.org/gwidams
[cid:image001.gif@01D13859.B03C1F30]<http://www.iucn.org/>
[cid:image002.jpg@01D13859.B03C1F30]<http://iucnworldconservationcongress.org/>
________________________________
This communication, together with any attachment, may contain confidential information and/or copyright material and is intended only for the person(s) to whom it is addressed. If you are not the intended recipient of this communication, or if you received it in error, you are asked to kindly delete it and promptly notify us. Any review, copying, use, disclosure or distribution of any part of this communication, unless duly authorized by or on behalf of IUCN, is strictly forbidden.
_______________________________________________
Dialoguebarrages mailing list
Dialoguebarrages(a)lists.dialoguebarrages.net
http://lists.dialoguebarrages.net/listinfo/dialoguebarrages
Dear colleagues,
We are pleased to share with you GWI’s article on the approval by the ECOWAS water ministers of the proposal for a directive on large water infrastructure. Please do share with any of your contacts who might be interested.
Best wishes,
---------------------------
ECOWAS water ministers agree to build fairer dams
GWI West Africa – 15/12/2015
The water ministers from the 15 countries that make up the Economic Commission of West African States (ECOWAS) have approved a proposal for a directive on large water infrastructure which would ensure future developments - particularly large dams - respect the environment and benefit all, including affected populations.
“The stated aim of the directive is to ‘ensure better consideration of environmental, economic and social considerations in the development of cross-border hydraulic infrastructure projects in West Africa in order to ensure their sustainability” says Mahamane Dédéou Touré from the ECOWAS Water Resources Coordination Unit.
In approving it, the region’s governments reaffirm their commitment to a shared and common approach to sustainable management of the water resources their populations rely on to survive.
In the context of climate change, energy and food production were high on the international agenda in Paris at COP21. They are also often the driving force behind the national and regional focus on costly and complex dam and irrigation projects — West Africa is already home to 150 dams and there are 40 more in planning or construction. But a look at past experiences in the region reveals that the benefits generated by dams rarely reach local people whose rights and livelihoods are most directly affected.
At Kandadji in Niger and at Samendéni in Burkina Faso, 38,000 and 40,000 people respectively are being displaced by the dams under construction. In Guinea, the Fomi dam will displace 48,000 people. Communities who host those displaced are also greatly affected.
Jamie Skinner, director of the Global Water Initiative in West Africa, says “if implemented, the directive will mark a tidal shift in the way dams are designed and built in West Africa, ensuring that both local and national populations share equitably in the benefits.”
Key elements of the directive include the need to ensure the informed participation of affected populations in decision-making as well as the use of stronger legal and procedural frameworks to grant local populations benefits such as agricultural land, electricity, drinking water, pasture and fisheries.
Following the water ministers’ approval, the directive will now need to be officially adopted by the ECOWAS Council of Ministers for it to be applied to its member states. States will then need to amend or adapt legislative, regulatory and other measures, where necessary, within three years from its entry into force. The ECOWAS will be responsible for evaluating the directive’s implementation every five years.
If governments and investors do not respect the directive, they risk driving those affected into deeper poverty or worse, sparking more conflict over land and natural resources. The risk of conflict is not restricted to national boundaries — most large infrastructure developments on West Africa’s rivers will affect more than one country. The role of transboundary basin organisations – such as the Niger River Basin Authority – are therefore recognised as highly important.
The directive was officially approved at the 4th ECOWAS session of the ministerial monitoring committee for integrated water resources management (IWRM) in West Africa, held in Dakar, Senegal, on Friday 27 November 2015, and chaired by Senegal’s ministry for water. It is based on the ‘Guidelines for the development of water infrastructure in West Africa’ developed through a two-year regional dialogue between member states, basin organisations and civil society that began in 2009, led by the ECOWAS Water Resources Coordination Unit, with the support of the International Union for Conservation of Nature (IUCN) and the International Institute for Environment and Development (IIED).
/ENDS
Related resources:
• TV report by Africable on the ECOWAS water ministers’ meeting and approval of the directive – in French [https://www.youtube.com/watch?v=rLc-M7nDuYA]
• Niger: a local fund to share the benefits of the Kandadji dam [GWI factsheet] http://gwiwestafrica.org/en/niger-local-fund-share-benefits-kandadji-dam
• Dams in Guinea: proposals for achieving local development [GWI factsheet] http://gwiwestafrica.org/en/dams-guinea-proposals-achieving-local-developme…
• ECOWAS Guidelines for the development of water infrastructure in West Africa http://cmsdata.iucn.org/downloads/ccre_cedeao_lignes_directrices_barrages_1…
• Barrage de Samendéni : Le cri du cœur des populations affectées [Press article – in French] http://lefaso.net/spip.php?article67654
Contact:
For more information, images and interviewees, contact: Lucile Robinson, Programme manager – knowledge management and communications (Global Water Initiative – West Africa), email: lucile.robinson(a)iied.org<mailto:lucile.robinson@iied.org>.
Notes to editors:
The 4th Session of the Ministerial Monitoring Committee of Integrated Water Resources Management (IWRM) in West Africa was preceded by the 10th Session of the Technical Expert Committee which took place on 24-25 November. The meetings were hosted by Senegal’s Ministry of Water and organised by the ECOWAS Water Resources Coordination Unit, IUCN and IIED. Funding has been provided by the ECOWAS Commission, the Howard G. Buffett Foundation through the Global Water Initiative (GWI) in West Africa, UK Aid (DFID) and the Swedish International Cooperation Agency (SIDA) through the PAGE Programme of IUCN.
For more information on the Global Water Initiative (GWI) in West Africa: www.gwiwestafrica.org<http://www.gwiwestafrica.org>
Jérôme KOUNDOUNO
Regional Coordinator
Global Water Initiative (GWI) - West Africa
International Union for Conservation of Nature
Dakar, Senegal
Tel : (+221) 77 102 53 57
www.gwiwestafrica.org<http://www.gwiwestafrica.org/>
www.iucn.org/gwidams
[cid:image001.gif@01D13859.C76D5110]<http://www.iucn.org/>
[cid:image002.jpg@01D13859.C76D5110]<http://iucnworldconservationcongress.org/>
________________________________
This communication, together with any attachment, may contain confidential information and/or copyright material and is intended only for the person(s) to whom it is addressed. If you are not the intended recipient of this communication, or if you received it in error, you are asked to kindly delete it and promptly notify us. Any review, copying, use, disclosure or distribution of any part of this communication, unless duly authorized by or on behalf of IUCN, is strictly forbidden.
_______________________________________________
Dialoguebarrages mailing list
Dialoguebarrages(a)lists.dialoguebarrages.net
http://lists.dialoguebarrages.net/listinfo/dialoguebarrages
From: Lionel Dabbadie [mailto:courriers.listes@gmail.com]
Sent: 15 December 2015 15:17
To: sarnissa-french-aquaculture Mailing List
Cc: sarnissa-african-aquaculture Mailing List
Subject: Re: [Sarnissa] Tilapia Hatchery and grow out project Madagascar Tilapia écloserie et grossissement des projets Madagascar
Bonjour,
MIDEM/Tilapia de l'Est is a beautiful project, using the technologies developed at the Asian Institute of Technology (http://aarm-asialink.info/ and http://www.serd.ait.ac.th/wpserd/aquaculture-and-aquatic-resources-manageme…) and with the expert support of Nam Sai Farm (http://www.tilapiathai.com). I confirm that any advise on how to get high quality feed in Madagascar at a competitive cost would be highly appreciated, as it is a limitation to the development of intensive & semi-intensive aquaculture, particularly in the (cold) highlands.
Ce projet MIDEM/Tilapia de l’Est est un très joli projet, qui utilise les techniques mises au point à l’Asian Institute of Technology (http://aarm-asialink.info/ and http://www.serd.ait.ac.th/wpserd/aquaculture-and-aquatic-resources-manageme…) et avec l’appui de Nam Sai Farm (http://www.tilapiathai.com). Je confirme que tout conseil sur l’obtention d’aliments de qualité à un prix compétitif serait d’une grande aide pour le développement de l’aquaculture à Madagascar, mais aussi probablement dans d’autres contextes, puisque c’est une des limites au développement de l’aquaculture semi-intensive et intensive, notamment dans les zones d’altitudes froides.
Bien amicalement/best regards
Lionel
Le 15 déc. 2015 à 16:34, William Leschen <william.leschen(a)stir.ac.uk<mailto:william.leschen@stir.ac.uk>> a écrit :
From: Sarnissa-french-aquaculture [mailto:sarnissa-french-aquaculture-bounces@lists.stir.ac.uk] On Behalf Of William Leschen
Sent: 15 December 2015 12:22
To: sarnissa-african-aquaculture Mailing List
Cc: sarnissa-french-aquaculture Mailing List
Subject: [Sarnissa] Tilapia Hatchery and grow out project Madagascar Tilapia écloserie et grossissement des projets Madagascar
Tilapia Hatchery and grow out project Madagascar Thanks to Loha for this
About the project: it's a project build by an NGO who is MIDEM(Mission Independante pour le Developpemnet et l'Education a Madagascar) funded by NORAD/NORGES VEL of Norway
With the target: to increase the income of farmers to 60 USD/month by fish farming(Tilapia). But using the local strain we didn't reach the target; slow growth, long cycle and low profitability) then we decide to import the GIFT and BIG NIN of Nam Sai Farm Thailand Co.Ltd on July 2013 and import feed from LFL Feed company Mauritius until now when the project become TILAPIA DE L'EST on Jan 2015.
Now we have 69 ponds working and 85 ponds under construction.
Our technical key indicators are:
Density on stocking: 3/ cubic m(All male Tilapia at 98%),semi intensive culture
Average pond dimension: 700 sq m or more
Average Mortality: 12%
Average FCR: 1.2
Period: 140 Days from at least 0.4g ABW of fingerlings on stocking
ABW per pond on harvest: 240g with an average of production at 350kg per pond
We are using the Asian method to get all male fingerlings using 17 alpha methyl testosterone>
We made protocols with our consultant from Norway Sir Morten Frost from pond building to harvest and commercialisation.
I'm now in charge on Broodstock management, eggs incubation, Sex reversal process, nursery and Packing and fingerlings delivery to farmers (transportation), so all about hatchery since 2011 and an integrated hatchery is now being built now.
But now our problem now is importation, we depend a lot on LFL Mauritius and USD exchange rates now increasing vis a vis of our money value then the cost of feed is very high for the farmers.
Then I've got the idea to create the first company in Madagascar who will provide the best feed quality for aquaculture at the lower possible price (the legendary floating pellet from Asia).
Our farmers will increase to reach 250 in number next year and the demand for feed will be higher. The target of TILAPIA DE L'EST by 2019 is 300 ponds and 600 by 2023 but 300 will be reached soon at least in the end of 2016 as we projected, because everyone wants to farm Tilapia with us now since it become profitable for them.
So if you know someone or an organisation who can fund this project to build a company for aquaculture feed let me know, it's a very big business opportunity down here now since the demand is very high.
I'm just talking about the Tilapia del'Est but a lot of other customers and other organisation like APDRA want this type of feed also. We are proud to be the first project who is successful in tilapia farming in Madagascar until now.
It's quite a long process ahead but it's all about us and aquaculture is developing down here.
Best Wishes,
Loha
Tilapia écloserie et grossissement des projets Madagascar Merci à Loha pour cette
À propos du projet: il est une construction du projet par une ONG qui est MIDEM (Mission Indépendante for the Developpement et l'éducation d'un Madagascar) financé par NORAD / NORGES VEL de la Norvège
Avec l'objectif: augmenter le revenu des agriculteurs de 60 USD / mois par la pisciculture (Tilapia). Mais l'utilisation de la souche locale nous n'a pas atteint la cible; croissance lente, cycle long et à faible rentabilité), alors nous décident d'importer le don et le BIG NIN de Nam Sai Farm Thaïlande Co. Ltd en Juillet 2013 et l'alimentation de l'importation de LFL Flux entreprise Maurice jusqu'à présent lorsque le projet devienne TILAPIA DE L'EST sur janvier 2015.
Maintenant, nous avons 69 étangs de travail et 85 étangs en construction.
Nos indicateurs clés techniques sont:
Densité de peuplement: 3 / m cube (tous de sexe masculin Tilapia à 98%), la culture semi-intensif
Étang moyenne dimension: 700 mètres carrés ou plus
La mortalité moyenne: 12%
Moyenne FCR: 1.2
Période: 140 jours d'au moins 0,4 g ABW d'alevins sur le stockage
ABW par étang sur la récolte: 240g avec une moyenne de production de 350 kg par étang
Nous utilisons la méthode asiatique pour obtenir tous les alevins mâles utilisant 17 alpha de testostérone de méthyle>
Nous avons des protocoles avec notre consultant de la Norvège Monsieur Morten Frost, de la construction de l'étang de récolter et de commercialisation.
Je suis maintenant en charge la gestion du stock de géniteurs sur, les oeufs d'incubation, le processus d'inversion de sexe, de pépinière et d'emballage et de la livraison des alevins aux agriculteurs (transport), de sorte que tous propos écloserie depuis 2011 et une écloserie intégrée est en cours de construction aujourd'hui.
Mais maintenant, notre problème est maintenant l'importation, nous dépendons beaucoup LFL Maurice et USD taux de change de plus en plus maintenant vis à vis de la valeur de notre argent, alors le coût des aliments est très élevé pour les agriculteurs.
Ensuite, je dois l'idée de créer la première entreprise à Madagascar qui fournira la meilleure qualité d'aliments pour l'aquaculture au prix inférieur possible (la légendaire de granulés flottants d'Asie).
Nos agriculteurs vont augmenter pour atteindre 250 en nombre l'année prochaine et la demande pour l'alimentation seront plus élevés. La cible du tilapia DE L'EST en 2019 est de 300 étangs et 600 d'ici 2023, mais 300 sera atteint dès au moins à la fin de 2016, comme nous avions prévu, parce que tout le monde veut cultiver Tilapia avec nous maintenant, car il devient rentable pour eux.
Donc, si vous connaissez quelqu'un ou une organisation qui peut financer ce projet de construction d'une société pour l'alimentation aquacole laissez-moi savoir, il est une très grande opportunité d'affaires ici aujourd'hui car la demande est très élevée.
Je parle simplement de l'Tilapia de l'Est, mais beaucoup d'autres clients et d'autres organisation comme APDRA veulent ce type d'alimentation aussi. Nous sommes fiers d'être le premier projet qui a réussi dans l'élevage du tilapia à Madagascar jusqu'à maintenant.
Il est un processus assez long avant mais il est tout autour de nous et de l'aquaculture se développe ici.
Amicalement
Loha
Institute of Aquaculture, University of Stirling UK
www.aqua.stir.ac.uk<http://www.aqua.stir.ac.uk/>
Follow Daily updated Facebook sites (news, publications, videos, employment, funding, investment and other) for:
Inst of Aquaculture Stirling Scotland UK<https://www.facebook.com/pages/Institute-of-Aquaculture-Stirling-Scotland-U…>
SARNISSA African Aquaculture Network <https://www.facebook.com/sarnissaafrica?ref=hl>
Aquaculture Enterprise Malawi<https://www.facebook.com/pages/Aquaculture-Enterprise-Malawi/57280560286237…>
SEAT Sustaining Ethical Aquaculture Trade Asia (SEAT) <https://www.facebook.com/SEATGlobal?ref=hl>
<image001.jpg><http://www.aqua.stir.ac.uk/> <image002.jpg>
<WP_20150206_008.jpg><WP_20150121_016.jpg><WP_20150121_017.jpg><WP_20150122_001.jpg><WP_20150128_007.jpg><WP_20150129_001.jpg><WP_20150129_002.jpg><WP_20150206_004.jpg><WP_20150206_005.jpg>_______________________________________________
Sarnissa-french-aquaculture mailing list
Sarnissa-french-aquaculture(a)lists.stir.ac.uk<mailto:Sarnissa-french-aquaculture@lists.stir.ac.uk>
http://lists.stir.ac.uk/cgi-bin/mailman/listinfo/sarnissa-french-aquaculture
English version below
Les ministres de l’eau de la CEDEAO s’accordent sur le renforcement de la coordination du secteur et approuvent la directive sur les infrastructures hydrauliques
Les 15 Ministres en charge des ressources en eau de la CEDEAO se sont réunis à Dakar le vendredi 27 novembre 2015 pour la 4ème Session du Comité Ministériel de Suivi (CMS) de la gestion intégrée des ressources en eau (GIRE) en Afrique de l’Ouest, sous la Présidence du Ministre de l’Hydraulique et de l’Assainissement du Sénégal.
« La présente session a porté sur des sujets d’importance capitale pour le mécanisme régional de coordination de la gestion intégrée des ressources en eau en Afrique de l’Ouest, dans lequel tous les États de la région sont résolument engagés » a déclaré M. Ousséini SALIFOU, représentant du commissaire chargé de l’agriculture, de l’environnement et des ressources en eau de la CEDEAO.
Le Comité Ministériel de Suivi a été l’occasion de faire le bilan de la mise en œuvre de la GIRE dans la région, d’échanger sur les initiatives menées par le Centre de Coordination des Ressources en Eau (CCRE) de la CEDEAO et ses partenaires, de définir les orientations de ses futures activités et renforcer les synergies d’action. Cette rencontre statutaire du Cadre Permanent de Coordination et de Suivi (CPCS) de la GIRE en Afrique de l’Ouest n’avait pas eu lieu depuis 2008.
Trouvez toutes les informations sur les décisions du CMS dans le communiqué de presse ci-joint ou sur le site web de l’UICN<http://www.iucn.org/fr/propos/union/secretariat/bureaux/paco/programmes/pre…>
________________________________
ECOWAS water ministers agree to strengthen coordination, and approve water management infrastructure policy
On Friday 27 November 2015 the 4th session of the Ministerial Monitoring Committee of the Integrated Water Resources Management (IWRM) initiative in West Africa was held in Dakar. It was chaired by the Minister of Water and Sanitation of Senegal.
According to M. Ousseini Salifou, representing the ECOWAS Commissioner for Agriculture, Environment and Water Resources: “this session covered key issues for the regional coordination of integrated water resources management in West Africa, to which all the governments of the region are whole-heartedly committed”.
The Ministerial Monitoring Committee reviewed progress in implementing IWRM in the region, discussed the initiatives carried out by the Water Resources Coordination Unit (WRCU) of ECOWAS and its partners, defined the orientations for future activities and took steps to strengthen the opportunities for synergies. This was the first statutory meeting of the Permanent Framework for IWRM Coordination and Monitoring (CPCS) in West Africa since 2008.
Find all the information on the decisions of CMS in the press release attached or on the IUCN website<http://www.iucn.org/fr/propos/union/secretariat/bureaux/paco/programmes/pre…>.
Marcello ROCCA
Expert en communication et valorisation des connaissances
"Partenariat pour la gouvernance environnementale
en Afrique de l'Ouest - PAGE"
Programme Afrique Centrale et Occidentale (PACO)
UICN (Union internationale pour la conservation de la nature)
01 BP 1618 Ouagadougou 01
Burkina Faso
Tel: +226 25 37 42 16 / 25 37 46 85
E-Mail : marcello.rocca(a)iucn.org<mailto:marcello.rocca@iucn.org>
www.uicn.org/prezoh<http://www.uicn.org/prezoh>
[cid:image001.gif@01D131A2.5A77D200]<http://www.iucn.org/>
[cid:image002.jpg@01D131A2.5A77D200]<http://iucnworldconservationcongress.org/>
________________________________
This communication, together with any attachment, may contain confidential information and/or copyright material and is intended only for the person(s) to whom it is addressed. If you are not the intended recipient of this communication, or if you received it in error, you are asked to kindly delete it and promptly notify us. Any review, copying, use, disclosure or distribution of any part of this communication, unless duly authorized by or on behalf of IUCN, is strictly forbidden.
_______________________________________________
Dialoguebarrages mailing list
Dialoguebarrages(a)lists.dialoguebarrages.net
http://lists.dialoguebarrages.net/listinfo/dialoguebarrages
Pouvez-vous nous en dire plus sur votre projet en Afrique de l'Ouest?
J. Lazard
-----Original Message-----
From: Jérôme LAZARD [mailto:jerome.lazard@cirad.fr]
Sent: 28 November 2015 10:54
To: sarnissa-french-aquaculture Mailing List
Subject: Re: [Sarnissa] Introducing myself to the Sarnissa community
Can you tell us more about your project in West Africa?
J. Lazard
----- Mail original -----
De: "Regis Gnonlonfoun" <regis.gnonlonfoun(a)gmail.com>
À: sarnissa-french-aquaculture(a)lists.stir.ac.uk
Envoyé: Samedi 28 Novembre 2015 09:00:29
Objet: [Sarnissa] Introducing myself to the Sarnissa community
Dear colleagues,
I would like to introduce myself as a new member of the Sarnissa community. I am very pleased to have joined and hope for further collaboration. I am a French engineer; I have been working at fish farms and aquaponic business in France, Brazil, Australia, Reunion Island and reared species as tilapia, barramundi, trout and catfish. I did pond farming and also made Recirculating Aquaculture System and their use for aquaponic my specialty. I am currently in mission at a semi-intensive, large scale, tilapia and heterotis farm in West Africa. Have a successful continuation.
Best regards
--
Régis GNONLONFOUN
General engineer - specialized in Aquaculture
_______________________________________________
Sarnissa-french-aquaculture mailing list
Sarnissa-french-aquaculture(a)lists.stir.ac.uk
http://lists.stir.ac.uk/cgi-bin/mailman/listinfo/sarnissa-french-aquaculture
Dear colleagues,
I would like to introduce myself as a new member of the Sarnissa community.
I am very pleased to have joined and hope for further collaboration. I am
a French engineer; I have been working at fish farms and aquaponic business
in France, Brazil, Australia, Reunion Island and reared species as tilapia,
barramundi, trout and catfish. I did pond farming and also made
Recirculating Aquaculture System and their use for aquaponic my specialty.
I am currently in mission at a semi-intensive, large scale, tilapia and
heterotis farm in West Africa. Have a successful continuation.
Best regards
--
*Régis GNONLONFOUN*
*General engineer - specialized in Aquaculture*